We have been moving in equipment and preparing for our renovation product. Monday we will begin
work on number 1 fairway bunker. We will remove the sand, liner, and gravel, the we will shape the bunker. During the shaping we will also move to number one green and repeat the process. The first hole will be about refining our procedure and expediting the process and efficiency. We will then move to number 2-3, this will allow holes 4-18 to remain open. Also we will be posting photos and updates to our website.