We have completed the drainage project at 9 fairway, the project consisted of over 1500 linear feet of drain tile and approximately 12 cubic yards of sand. One issue we were dealing with, was a spring which had popped up in the right rough. This spring was flowing at a rate of about 4-5 gallons per minute. We have plumbed the spring into our drainage eliminating the constant supply of water. The drainage we installed is the same as 17 fairway, a slotted pipe with a semi-permeable sock around it which allows water to pass through but not sand. Next time you play take a look inside the catch basins to see the the water flowing.